Build Guide: Lake Lotawana, Missouri

Two permits, two organizations, two calendars. The Association owns the lake and the ground along its edge.

Lake Lotawana is an incorporated fourth-class city of about 2,300 residents in Jackson County, Missouri, southeast of Kansas City between Lee’s Summit and Greenwood. The lake itself is private and is owned and controlled by the Lake Lotawana Association, not by the city. The city calls it the largest private lake in the Kansas City area. Building here means dealing with both bodies, and they are genuinely separate.

Faust Construction builds new homes, additions, and whole-house renovations at Lake Lotawana and across the Kansas City metro.

What defines Lake Lotawana

The Lake Lotawana Development Company incorporated on December 30, 1927 and began building the dam, which was finished in the fall of 1929. Drought delayed full pool until the spring of 1935. The Lake Lotawana Association was incorporated in 1932, and in 1988 a settlement gave the Association ownership and complete control of the lake. The city itself incorporated in 1958 and runs a mayor and six-alderman government.

The city describes 480 acres of surface water and 27 miles of shoreline, with roughly 1,200 residences. The original 1920s plat was drawn for summer cottages, which is why so many lakefront lots are small and steep by modern standards, and why the current market is heavily weighted toward teardown rebuilds and substantial renovations rather than additions.

The detail that shapes almost every lakefront project is the Parkway: the strip of ground the Association owns between the platted lots and the water. On most lakefront properties the lot line does not reach the lake. That single fact reorders how a dock, a seawall, stairs, or shoreline grading gets planned and who has to approve it.

Building at Lake Lotawana

What homeowners should know

A Lake Lotawana project needs two permits from two organizations on two calendars. The requirements below come from the city’s Permits page and its municipal code, and from the Lake Lotawana Association.

On this page

Two permits, two calendars

The city issues the building permit through its Planning and Zoning Administrator: no wall, structure, or building may be built, enlarged, or altered within the city limits without one. The Association separately issues its own construction permit, and it covers a wide range: new houses, additions, garages, roofs, decks, patios, fences, pools, stairs, demolition, and all dock, lift, seawall, structural wall, and shoreline work.

Association permits are reviewed by the Lake Improvement Board, which hears cases on the fourth Thursday of the month on a first-come basis and is capped at fifteen cases per month. Miss the docket and the project slips a month. The Association also requires that all dues and any other amounts owed be paid before an application is processed, which means an owner’s unpaid dues can hold up a builder’s schedule.

The city’s own permit page acknowledges the split and recommends contacting the Association at (816) 578-4272 about their permitting requirements for the Lakeside Residential district.

Seawalls are an Association approval only

All construction and repair of seawalls and retaining walls must be approved by the Lake Improvement Board. The city’s code chapter on the lake contains no seawall provisions at all. If a project involves shoreline stabilization, the Association is the approving body, not the city.

Docks answer to two rulebooks with different numbers

The city requires a building permit from the Building Commissioner for any boat dock, boathouse, boat lift, catwalk, or other docking structure, and will not issue one to an applicant who does not own real estate in the Lakeside Residential district improved with habitable living quarters. Under city rules a docking structure may not project more than 40 feet from the shoreline including the catwalk, must maintain 15 feet from adjacent docking structures, and the deck may not exceed three feet above the water.

The Association’s own rules set a different envelope: a maximum 36 feet wide by 28 feet long measured perpendicular from the shoreline, the same three-foot deck height, and no enclosed boathouses for new construction. The Association also states that no dock permit will be issued to any property without inhabitable living quarters connected to an approved sewer system.

The practical consequence is that on a new build, the dock is downstream of the house and the sewer connection. It cannot be permitted first.

This is a sewer town, not a septic town

Lake Lotawana operates its own sewer system with 24 lift stations and a treatment plant, serving roughly 1,200 customers. Where a public sewer is within 100 feet of the property line, the owner is required to connect at their own expense. The code expressly prohibits the construction or use of private sewage disposal facilities such as septic tanks, with narrow exceptions for pre-1976 and annexed systems and for new houses where the city sewer lacks capacity and the Board approves.

If you have built at other Missouri lakes, this is the assumption to drop. There is no Jackson County septic permit in the path for a normal in-city lot here.

Permits, codes, and inspections

City building permits carry a twelve-month maximum duration, extendable at the discretion of the Director of Public Works. Two sets of construction documents by registered design professionals are required, and plan review fees are charged and credited toward permit issuance. The city has adopted the 2018 International Building Code with Appendix H, the 2018 International Residential, Mechanical, Plumbing, and Fuel Gas Codes, the 2018 International Fire Code, and the 2017 National Electrical Code.

Building inspections are performed under contract by IBTS and right of way, driveway, and sidewalk work by Lamp Rynearson. Work hours are 7 a.m. to 7 p.m. weekdays and 8 a.m. to 6 p.m. weekends.

Zoning and licensing

The city has five residential districts: Estate, Low Density, Medium Density, Lakeside, and Town House. Lakeside Residential is the higher-density single-family district around the lake, and it sets minimum floor areas: a one-story house with a full basement needs at least 900 square feet on the main floor, a one-story without a basement at least 1,200, and a two-story at least 900 on the main floor.

Setbacks, minimum lot size, height, and lot coverage live in Exhibit 415-A, an attachment to the zoning chapter that is not publicly retrievable. We have not published those numbers rather than guess at them. Get Exhibit 415-A and the fee schedule from City Hall before a design is fixed.

On licensing, Missouri has no statewide general contractor license. Lake Lotawana requires a city business license for all contractors and subcontractors doing business in the city, plus trade certificates of qualification for HVAC, master plumbing, and master electrical work.

ItemCity of Lake LotawanaLake Lotawana Association
House, addition, garage, deckBuilding permit requiredConstruction permit required
Dock projectionMax. 40 ft. from shoreline including catwalkMax. 36 ft. wide by 28 ft. long from shoreline
Dock spacing15 ft. between adjacent structuresConfirm with the Association
Dock deck heightMax. 3 ft. above waterMax. 3 ft. above water level
Seawalls and retaining wallsNo provision in city codeLake Improvement Board approval
Review schedulePlanning and Zoning Administrator4th Thursday, first come, 15 cases per month
Permit duration12 months maximumConfirm with the Association

Why Lake Lotawana projects take local experience

Faust Construction has built in the Kansas City metro for more than 25 years, including work at Lake Lotawana. The mistake people make here is treating it as one approval process. It is two, run by two organizations, with different rules for the same dock and a monthly cap on how many cases the Association will hear.

Our pre-construction phase sequences that properly: Association construction permit and city building permit lined up against the Lake Improvement Board calendar, dock and seawall scope separated out because the Association controls the shoreline, the sewer connection scheduled ahead of the dock because the dock permit depends on it, and the Parkway boundary confirmed on the survey before anything is designed at the water’s edge.

Pre-construction

We price the design, evaluate materials and alternatives, and build a schedule that accounts for city review milestones.

Construction

We work with a consistent group of craftsmen and trade partners, with daily on-site presence throughout the build.

Management

We track cost against budget transparently and meet monthly with the architect and homeowner.

What we build at Lake Lotawana

Lake Lotawana is a 1920s cottage plat that has been steadily rebuilt into a year-round lake community, so most work is a rebuild or a substantial renovation on a tight, sloping lakefront lot.

  • Teardown rebuilds. New lakefront houses on original platted lots, sized against the Lakeside Residential minimum floor areas and the site constraints the old plat left behind.
  • Whole-house renovations. Converting an original cottage into a year-round home, with systems, insulation, and layout brought up to current expectations.
  • Additions. Expansions on lots where the buildable area is limited by grade and by the Association-owned Parkway between the lot line and the water.
  • Shoreline and dock work. Seawalls, stairs, and docking structures, which run through the Lake Improvement Board and, for docks, the city as well.

Faust Construction works across the Kansas City metro on both sides of the state line, including the lake communities southeast of the city. Lake Lotawana sits inside our regular service area alongside Lake Winnebago, Lakewood, Lee’s Summit, and the Kansas City, Missouri neighborhoods along Ward Parkway.

Recent work

Browse new construction, additions, and full-home renovations from across the Kansas City metro, including projects in established neighborhoods that share this area’s scale and housing stock.

View our projects
Frequently asked

Questions about building here

Answers to what homeowners ask before starting a project in this area.

Who owns Lake Lotawana?

The Lake Lotawana Association owns and controls the lake, not the city. The Lake Lotawana Development Company built it starting in 1927, the Association was incorporated in 1932, and a 1988 settlement gave the Association ownership and complete control. The City of Lake Lotawana is a separate incorporated fourth-class city, formed in 1958, in Jackson County, Missouri. The city describes 480 acres of surface water and 27 miles of shoreline.

Do I need two permits to build at Lake Lotawana?

Yes. The city issues a building permit through its Planning and Zoning Administrator, and the Lake Lotawana Association separately issues a construction permit covering houses, additions, garages, roofs, decks, patios, fences, pools, stairs, demolition, docks, lifts, seawalls, and shoreline work. Association permits are reviewed by the Lake Improvement Board, which hears cases on the fourth Thursday of the month on a first-come basis and is capped at fifteen cases per month. Association dues must be paid current before an application is processed.

Does my Lake Lotawana lot reach the water?

Usually not. The Association owns a strip of ground called the Parkway between the platted lots and the lake, so on most lakefront properties the lot line stops short of the water. That means a dock, seawall, set of stairs, retaining wall, or any shoreline grading sits on or crosses Association ground and needs Association approval. Confirm the Parkway boundary on the survey before designing anything at the water’s edge.

Who approves docks and seawalls at Lake Lotawana?

Seawalls and retaining walls are approved by the Association’s Lake Improvement Board; the city’s lake chapter has no seawall provisions at all. Docks need both. City rules limit a docking structure to 40 feet of projection from the shoreline including the catwalk, 15 feet of separation from adjacent structures, and a deck no more than three feet above the water. The Association sets a maximum 36 feet wide by 28 feet long envelope and does not permit enclosed boathouses for new construction. The Association also will not issue a dock permit for a property without habitable living quarters connected to an approved sewer system.

Is Lake Lotawana on septic or city sewer?

City sewer. Lake Lotawana operates its own system with 24 lift stations and a treatment plant serving roughly 1,200 customers. Where a public sewer is within 100 feet of the property line, the owner is required to connect at their own expense, and the code expressly prohibits septic tanks and other private sewage disposal facilities except in narrow grandfathered or capacity-limited cases. There is no Jackson County septic permit in the path for a normal in-city lot.

Does Faust Construction build at Lake Lotawana, Missouri?

Yes. Faust Construction is based in Lee’s Summit and works across the Kansas City metro on both sides of the state line, including the lake communities southeast of the city. Lake Lotawana sits inside its regular service area alongside Lake Winnebago, Lakewood, and the Kansas City, Missouri neighborhoods. Brian Faust founded the company more than 25 years ago.